Completed Projects 2010 - Present

County Leg District Project Type Road Name Project # Funded RATA Amount Date Completed
Franklin 9 Reconstruction R-170 ROAD 1109-01 $1,202,957 $1,202,957 2012
Adams 9 Rehabilitate, Resurface, Restore DANEKAS ROAD 0109-01 $2,393,700 $1,831,209 2016
Garfield 9 Rehabilitate, Resurface, Restore PEOLA ROAD 1207-01 $2,800,000 $2,800,000 2013
Adams 9 Reconstruction LIND - HATTON #4 0107-01 $2,162,400 $2,162,400 2014
Adams 9 Resurface and Restore Marcellus 0113-01 $750,000 $750,000 2016
Franklin 9 Federal-Aid Bridge R-170 Road; Bridge 608-2.35 1113-01 $217,000 $186,069 2015
Whitman 9 Resurface and Restore Thorn Creek Road 3813-01 $586,000 $586,000 2014
Adams 9 Federal-Aid Bridge McManamon 0114-01 $429,400 $422,831 2020
Garfield 9 Rehabilitate, Resurface, Restore Gould City Mayview rd 1213-01 $1,492,200 $1,492,200 2016
Whitman 9 Resurface and Restore Farmington Road 3816-02 $750,000 $750,000 2017
Adams 9 Resurface and Restore Cunningham 0115-01 $922,500 $922,500 2018
Adams 9 Resurface and Restore Lind-Hatton 0117-01 $361,800 $361,800 2021
Adams 9 Resurface and Restore Cunningham 0117-02 $901,000 $901,000 2022
Franklin 9 Federal-Aid Bridge TAYLOR FLATS BRIDGE #903-3.46 1118-01 $117,800 $117,800 2019
Franklin 9 Federal-Aid Bridge COYAN BRIDGE #200-9.93 1118-02 $222,700 $222,700 2021
Franklin 9 Federal-Aid Bridge SELPH LANDING BRIDGE #906-8.79 1118-03 $72,600 $72,600 2021
Garfield 9 Rehabilitate, Resurface, Restore Gould City Mayview Phase 4 1215-01 $1,572,800 $1,572,800 2021
Adams 9 Resurface and Restore McKinney Rd. #1 0119-01 $1,067,400 $1,067,400 2023
Ferry 7 Rehabilitate, Resurface, Restore BRIDGE CREEK 4 1005-01 $1,139,900 $939,488 2012
Stevens 7 Rehabilitate, Resurface, Restore ALADDIN RD 1 3307-01 $1,669,500 $1,450,364 2014
Lincoln 7 Rehabilitate, Resurface, Restore OLD COULEE ROAD 2209-01 $1,174,000 $1,010,198 2014
Pend Oreille 7 Rehabilitate, Resurface, Restore FERTILE VALLEY ROAD 2610-01 $2,087,000 $2,036,060 2022
Stevens 7 Reconstruction ALADDIN 3309-01 $1,694,700 $1,694,700 2014
Stevens 7 Reconstruction BLUE CREEK ROAD 2 3303-03 $2,212,000 $2,212,000 2012
Ferry 7 Rehabilitate, Resurface, Restore BRIDGE CREEK 12 1009-01 $1,800,000 $1,391,356 2016