Active by Status

County Leg District Project Type Road Name Project # Funded RATA Amount Date Completed
Adams 9 Reconstruction Lind Hatton Rd. Project #3 0119-02 $2,808,060 $2,808,060 2025
Asotin 9 Resurface and Restore Snake River Road 0215-01 $2,400,000 $2,400,000 2023
Chelan 12 Rehabilitate, Resurface, Restore Goodwin Road 0419-02 $1,377,000 $1,240,505 2025
Chelan 12 Resurface and Restore Chumstick Highway 0421-01 $1,045,000 $1,044,999 2023
Chelan 12 Resurface and Restore Wenatchee Heights Road 0423-01 $1,374,000 $1,213,698
Cowlitz 20 Rehabilitate, Resurface, Restore South Cloverdale Road 0815-01 $1,300,000 $183,228
Ferry 7 Resurface and Restore Cache Creek 1023-01 $1,905,500 $1,716,844
Ferry 7 Local Bridge East Silver Creek Br. No. 16 1021-01 $2,165,000 $862,836
Franklin 9 Federal-Aid Bridge Hollingsworth Bridge #460-6.2 1122-02 $205,300 $143,718
Grant 13 Resurface and Restore Stratford Road (12-NE to 16-NE) 1317-01 $750,000 $750,000
Grant 13 Resurface and Restore Stratford Road (20-NE to RRX) 1319-01 $750,000 $186,721
Grant 13 Resurface and Restore 3-NE (U-NE to County Line) 1321-01 $698,400 $698,400
Grant 13 Reconstruction 9-NW Road (SR 283 to Dodson Rd 1322-01 $2,103,000 $2,103,000 2024
Grant 13 Reconstruction H-SE (12-SE to SR 262) 1319-02 $2,750,000 $2,750,000 2025
Grays Harbor 19 Reconstruction Garrard Creek Road Realignment 1415-01 $1,460,000 $1,460,000 2024
King 31 Drainage Structure SE 384th St 1721-01 $1,035,000 $1,035,000
King 5 Local Bridge Ames Lake Road Bridge No.1320A 1719-01 $2,888,900 $2,888,900 2024
Kitsap 35 Rehabilitate, Resurface, Restore Seabeck Highway # 2 1816-01 $1,800,000 $1,800,000 2022
Kitsap 35 Rehabilitate, Resurface, Restore Glenwood Road SW Improvements 1819-01 $2,142,000 $2,867
Klickitat 14 Resurface and Restore Sunnyside Road 2023-02 $2,580,000 $1,312,683
Klickitat 14 Reconstruction Sundale Road & Old Hwy 8 2019-01 $5,321,213 $5,321,213 2025
Lewis 20 Reconstruction Centralia Alpha 2119-01 $2,444,400 $2,430,667
Lewis 20 Resurface and Restore Barnes Dr 2123-01 $1,215,000 $685,189
Lewis 20 Rehabilitate, Resurface, Restore Bunker Creek 2124-01 $1,550,000 $312,968
Lincoln 13 Drainage Structure Mohler 2223-01 $390,600 $377,660