Garfield - Kirby-Mayview

Project Number: 1223-01
From milepost 13.2 to milepost 15.16
RATA Funds: $1,500,000
Legislative District: 9
Status: PE and Design
Date Approved: 2023
This project is a significant farm to market road. Also this road is a primary access road from Clarkston to Lower Granite Dam and juvenile fish facilities and Snake River. It is ranked one of the highest priority travel and freight corridors in our community. The most prominent deficiencies include roadway width, safety. rough ride, inadequate ballast and pavement section. A significant amount of public involvement has occurred in the project selection and ranking process.

Work will include subgrade repair, horiz curve correction, roadway and shoulder widening, slope flattening, guardrail, hazard elimination(trees, roadside hazards, slopes), new roadway ballast and surfacing, BST, drainage, signing, striping, seeding, fertilizing and mulching.