Completed Projects 2010 - Present

County Leg District Project Type Road Name Project # Funded RATA Amount Date Completed
Grant 13 Reconstruction 4-NE (Hiawatha to Westshore Dr.) 1315-03 $1,193,400 $1,193,400 2019
Grant 13 Reconstruction 4-NE (N-NE to L-NE) 1315-02 $995,400 $947,120 2019
Grant 13 Reconstruction 6-SE ROAD 1307-03 $825,525 $825,525 2014
Grant 13 Reconstruction 7-NE (Stratford Rd. to M-NE) 1313-02 $1,048,500 $1,048,500 2014
Grant 13 Resurface and Restore 9-NW (Quincy City Limits to Adams Rd) 1315-01 $750,000 $750,000 2017
Grant 13 Rehabilitate, Resurface, Restore 11 SW ROAD 1310-01 $1,323,900 $1,088,829 2012
Snohomish 39 Intersection 84 St NE 3117-01 $584,100 $584,100 2021
Pierce 2 Resurface and Restore 304 Street East 2717-01 $603,900 $470,620 2019
Grant 13 Reconstruction Adams Road 1313-03 $1,030,500 $1,030,500 2017
Stevens 7 Reconstruction ALADDIN 3309-01 $1,694,700 $1,694,700 2014
Stevens 7 Rehabilitate, Resurface, Restore ALADDIN RD 1 3307-01 $1,669,500 $1,450,364 2014
Stevens 7 Rehabilitate, Resurface, Restore Aladdin Road MP 19.6 to 22.5 3313-01 $2,025,100 $2,025,100 2017
Whitman 9 Rehabilitate, Resurface, Restore ALMOTA ROAD 2 3807-01 $2,907,000 $2,515,977 2011
Stevens 7 Emergency Arden Bridge Emergency Replacement 3311-01 $650,000 $650,000 2013
Spokane 4 Resurface and Restore Argonne Road 3217-01 $750,000 $542,851 2019
Spokane 4 Reconstruction BIGELOW GULCH RD 4 3207-01 $5,987,480 $5,987,480 2019
Spokane 4 Reconstruction Bigelow Gulch Road 3215-01 $2,579,100 $2,579,100 2022
Whatcom 42 Reconstruction BIRCH BAY - LINDEN ROAD 3707-01 $750,000 $750,000 2014
Whatcom 42 Resurface and Restore Birch Bay Lynden Road 3719-02 $675,000 $675,000 2022
Stevens 7 Reconstruction BLUE CREEK ROAD 2 3303-03 $2,212,000 $2,212,000 2012
Grays Harbor 19 Reconstruction Blue Slough Road Realignment 1413-01 $900,000 $900,000 2021
Island 10 Rehabilitate, Resurface, Restore Boon Road 1514-01 $2,046,000 $1,594,204 2020
Island 10 Rehabilitate, Resurface, Restore BOON ROAD - 1 1507-01 $750,000 $750,000 2016
Skagit 40 Rehabilitate, Resurface, Restore Bow Hill Road 2913-01 $2,306,700 $2,306,700 2022
Ferry 7 Rehabilitate, Resurface, Restore BRIDGE CREEK 4 1005-01 $1,139,900 $939,488 2012