Adams |
9 |
Reconstruction |
Lind Hatton Rd. Project #3 |
0119-02 |
$2,309,400 |
$33,227 |
|
Adams |
15 |
Reconstruction |
Herman Road #2 |
0123-01 |
$2,453,275 |
$108 |
|
Asotin |
9 |
Local Bridge |
Grande Ronde Road |
0219-01 |
$1,685,700 |
$359,586 |
|
Asotin |
9 |
Rehabilitate, Resurface, Restore |
Snake River Road |
0223-01 |
$1,376,100 |
$21,806 |
|
Benton |
8 |
Reconstruction |
Hanks Road Phase I |
0317-01 |
$1,400,000 |
$98,961 |
|
Benton |
16 |
Rehabilitate, Resurface, Restore |
County Well Road |
0323-01 |
$442,459 |
|
|
Chelan |
12 |
Rehabilitate, Resurface, Restore |
Squilchuck Road |
0423-02 |
$1,032,100 |
|
|
Chelan |
12 |
Rehabilitate, Resurface, Restore |
South Lakeshore Road |
0422-01 |
$1,844,100 |
$19,741 |
|
Chelan |
12 |
Resurface and Restore |
Wenatchee Heights Road |
0423-01 |
$1,236,600 |
$10,842 |
|
Clallam |
24 |
Resurface and Restore |
Carlsborg Road |
0519-01 |
$472,500 |
$21,814 |
|
Clallam |
24 |
Rehabilitate, Resurface, Restore |
Edgewood Drive |
0523-01 |
$111,360 |
|
|
Clark |
18 |
Resurface and Restore |
SE Blair Road |
0619-01 |
$1,509,000 |
$101,975 |
|
Clark |
17 |
Resurface and Restore |
NE 182nd Avenue/NE Risto Road |
0623-01 |
$460,712 |
|
|
Columbia |
16 |
Federal-Aid Bridge |
Kellogg Hollow Rd - Starbuck B |
0719-01 |
$695,300 |
$65,973 |
|
Columbia |
16 |
Rehabilitate, Resurface, Restore |
Kellogg Hollow Rd |
0719-02 |
$2,104,700 |
$63,339 |
|
Columbia |
5 |
Rehabilitate, Resurface, Restore |
Kellogg Hollow Road |
0723-01 |
$1,600,000 |
$7,105 |
|
Cowlitz |
20 |
Rehabilitate, Resurface, Restore |
South Cloverdale Road |
0815-01 |
$1,300,000 |
$183,228 |
|
Cowlitz |
20 |
Resurface and Restore |
Dike Road |
0819-01 |
$1,692,000 |
$98,709 |
|
Cowlitz |
20 |
Drainage Structure |
Rose Valley Road |
0823-01 |
$500,000 |
$20,142 |
|
Cowlitz |
20 |
Drainage Structure |
Powell Road |
0823-02 |
$500,000 |
|
|
Cowlitz |
20 |
Drainage Structure |
Cloverdale Road |
0823-03 |
$500,000 |
|
|
Douglas |
12 |
Rehabilitate, Resurface, Restore |
Rd J.5 NW |
0923-01 |
$873,250 |
$16,542 |
|
Douglas |
12 |
Reconstruction |
McNeil Canyon Rd |
0922-01 |
$2,653,200 |
$105,787 |
|
Ferry |
7 |
Rehabilitate, Resurface, Restore |
Trout Creek Road Section 1 |
1019-03 |
$1,813,500 |
$8,191 |
|
Ferry |
7 |
Resurface and Restore |
Cache Creek |
1023-01 |
$750,000 |
$5,527 |
|