Active Projects Status

Funded projects are projects that have gained RATA funding and are in Design or Construction phase. Proposed projects are those the county is requesting funding for.

The chart below depicts the status of RAP funded and proposed projects.

Click on the view links in the table below to display projects in construction, design, or are proposed.



Active Project Status
Type # of Projects Status
Design 109 Projects in Design View
Construction 39 Projects in Construction View
Proposed 27 Proposed Projects View

Please contact Grants@Crab for more information.

Top

109 Projects in Design Status

[ Previous Page 1 2 3 4 5 6 Next Page ]



Projects in Design Status
Region County Leg Dist Status Project Name Project# ProjectType Truck Approval Date
1 NE Okanogan 12 PE and Design Salmon Cr Rd Drainage 2419-01 Drainage Structure Non 2019
2 NE Adams 9 PE and Design McKinney Rd. #1 0119-01 Resurface and Restore T3 2019
3 NE Grant 13 PE and Design Stratford Road (20-NE to RRX) 1319-01 Resurface and Restore T4 2019
4 NE Ferry 7 PE and Design Klondike Road Rehabilitation 1019-01 Resurface and Restore T4 2019
5 NE Chelan 12 PE and Design Mission Creek Road 0419-01 Resurface and Restore Non 2019
6 NE Whitman 9 PE and Design Johnson Cut Off Road 3819-01 Resurface and Restore T4 2019
7 NE Spokane 7 PE and Design Brooks Road Project No. 2 3219-01 Rehabilitate, Resurface, Restore T3 2019
8 NE Chelan 12 PE and Design Goodwin Road 0419-02 Rehabilitate, Resurface, Restore T4 2019
9 NE Lincoln 13 PE and Design Miles Creston Road Section 1B 2219-01 Rehabilitate, Resurface, Restore T3 2019
10 NE Okanogan 12 PE and Design Old 97 2419-02 Rehabilitate, Resurface, Restore T3 2019
11 NE Stevens 7 PE and Design Cedonia-Addy 3319-01 Rehabilitate, Resurface, Restore T4 2019
12 NE Whitman 9 PE and Design Pullman Airport Road 3819-02 Reconstruction T3 2019
13 NE Adams 9 PE and Design Lind Hatton Rd. Project #3 0119-02 Reconstruction T4 2019
14 NE Grant 13 PE and Design H-SE (12-SE to SR 262) 1319-02 Reconstruction T4 2019
15 NE Ferry 7 PE and Design Inchelium Hiway Rehabilitation 1019-02 Resurface and Restore T3 2019
16 NE Ferry 7 PE and Design Trout Creek Road Section 1 1019-03 Rehabilitate, Resurface, Restore Non 2019
17 NE Okanogan 12 PE and Design Statler Br Emergency Replacement 2418-01 Emergency Non 2018
18 NE Lincoln 13 PE and Design Miles Creston 2218-02 Rehabilitate, Resurface, Restore T3 2018
19 NE Stevens 7 PE and Design Hall Road Bridge Replacement 3318-01 Federal-Aid Bridge Non 2018
20 NE Ferry 7 PE and Design Bridge Creek Section 13 1017-02 Rehabilitate, Resurface, Restore T1 2017
21 NE Okanogan 12 PE and Design Cameron Lake Rd 2417-02 Reconstruction T4 2017
Top

39 projects in Construction Status


[ Previous Page 1 2 Next Page ]

Projects in Construction
Region County Leg Dist Status Project Name Project# ProjectType Truck Funded Rata Amount
1 NE Lincoln 13 Construction Porcupine Bay Road 2218-03 Emergency Non $ 638,300 $ 579,726
2 NE Spokane 4 Construction Argonne Road 3217-01 Resurface and Restore T1 $ 750,000 $ 542,851
3 NE Ferry 7 Construction Silver Creek, Sec. 1 1015-01 Resurface and Restore T4 $ 648,000 $ 36,618
4 NE Okanogan 7 Construction Highway 7 2415-01 Resurface and Restore T3 $ 540,000 $ 178,119
5 NE Grant 13 Construction 4-NE (N-NE to L-NE) 1315-02 Reconstruction T4 $ 995,400 $ 947,120
6 NE Grant 13 Construction 4-NE (Hiawatha to Westshore Dr.) 1315-03 Reconstruction T4 $ 1,193,400 $ 62,774
7 NE Ferry 7 Construction Inchelium Hwy 1014-01 Rehabilitate, Resurface, Restore T3 $ 1,800,000 $ 1,388,928
8 NE Adams 9 Construction McManamon 0114-01 Federal-Aid Bridge Non $ 429,400 $ 370,839
9 NE Pend Oreille 7 Construction Sullivan Lake Inlet Bridge 2613-01 Federal-Aid Bridge T5 $ 173,000 $ 173,000
10 NE Lincoln 7 Construction Old Coulee Road Section 2 2213-02 Reconstruction T4 $ 2,025,000 $ 1,960,544
11 NE Pend Oreille 7 Construction Coyote Trail 2613-02 Resurface and Restore T4 $ 730,800 $ 643,871
12 NE Pend Oreille 7 Construction FERTILE VALLEY ROAD 2610-01 Rehabilitate, Resurface, Restore T3 $ 2,087,000 $ 1,812,112
13 NE Whitman 9 Construction ALMOTA ROAD 4 3810-01 Rehabilitate, Resurface, Restore T4 $ 2,500,000 $ 269,968
14 NE Spokane 4 Construction FORKER ROAD 3210-01 Reconstruction T2 $ 5,000,000 $ 3,144,276
15 NE Spokane 4 Construction BIGELOW GULCH RD 4 3207-01 Reconstruction T2 $ 5,987,480 $ 4,711,255
16 NE Spokane 4 Construction BIGELOW GULCH ROAD 3298-01 Reconstruction T2 $ 2,745,000 $ 1,140,976
17 NW Jefferson 24 Construction Upper Hoh Road 1618-03 Emergency T4 $ 336,500 $ 336,500
18 NW Jefferson 24 Construction South Discovery Road Pavement Preservation 1615-01 Resurface and Restore Non $ 450,000 $ 42,607
19 NW Island 10 Construction Boon Road 1514-01 Rehabilitate, Resurface, Restore Non $ 2,046,000 $ 1,797,463
20 NW San Juan 40 Construction Orcas Road 2813-01 Rehabilitate, Resurface, Restore T3 $ 2,587,500 $ 1,737,434
21 NW Island 10 Construction BOON ROAD - 1 1507-01 Rehabilitate, Resurface, Restore Non $ 750,000 $ 750,000