Active Project Report

Courtney Road Project

Klickitat County - Courtney Road

Project Number: 2016-01
From Milepost: 0.000 - To Milepost: 2.150
RATA funds: $ 990,000
Legislative District: 14
Status PE and Design
Date Approved: 2016

The existing ashalt surface on Courtney Road needs to be restored. The project will restore the asphalt surface by grinding the existing BST surface and grading it in place. Two 1.5" lifts of HMA will be placed. The project will include minor widening to establish a minimum 22 foot travel way. Fixed objects will be removed from the clearzone where feasable and slope flattening or guardrail will be added where needed.

Before image not on file.